Bridge Scaffolding Project - Boat of Brig, Fochabers

Working alongside Morrison Construction to provide full containment to the bridge the structure was completely contained with a Haki underdeck system and full Haki roof.

The under deck was a specially designed suspended scaffold utilising the impressive Haki 750 aluminium beam system onto which Haki steel deck were placed to form a robust working platform. As the river Spey is a very important salmon river a special permeable membrane was used to contain the shot blast and paint reside from contaminating the river below.

A full Haki roof was constructed to form a temperature-controlled environment to allow the bridge coating to cure.

The project duration was 20 weeks and was completed within time and budget.

Return to Projects

Scaffolding Services

Scaffolding Services

 

Get in Touch with Abscaff

Abscaff are leading suppliers of Scaffolding Supplies and Equipment from our base in Aberdeen throughout Scotland. To find out how Abscaff can help with your scaffolding requirements please call us today.

 01224 592 629
 info@abscaff.co.uk
 Online Enquiry Form